Construction Updates
If you have questions about any district construction projects, please contact Jeff Ohmart with MMWD's engineering Division at 415-945-1574 or johmart@marinwater.org.
2018 - 19
April - October 2019: Almonte and Homestead
MMWD will install new pipelines in various streets including Rosemont Avenue, Greenhill Road and Almonte Boulevard in the unincorporated communities of Almonte and Homestead. Learn more. Update 6/24/2019: The contractor, Michael Paul Company, is still working on Almonte Blvd. They are working their way from Miller Avenue to Stadium Drive with traffic control in place. Construction should be in progress on Almonte until mid to late July.
April - October 2019: San Anselmo and Ross
MMWD is replacing pipeline installed as early as 1903 in the Towns of Ross and San Anselmo on Baywood Avenue, Crest Road and Wellington Avenue. Learn more.
August - October 2019: Ross Reservoir Bypass Pipeline Replacement Project
MMWD is installing new pipelines on Worn Spring Road near Phoenix Lake on MMWD watershed land. Passage through Worn Springs Road at Ross Reservoir will be closed during construction due to heavy equipment and trucks entering and exiting the worksite.
July - September 2019: Corte Madera Fire Flow Improvement
MMWD will install new pipelines on Sausalito Street from Madrono Avenue to South Way in the Town of Corte Madera. Learn more.
Recently Completed
March - May 2019: Bolinas Avenue, San Anselmo
MMWD will install new pipeline and service laterals on Bolinas Avenue in the Town of San Anselmo. Learn more.
November - March 2019: San Francisco Blvd Pipeline Replacement
MMWD is installing new pipeline on San Francisco Blvd in the Town of San Anselmo. Watch this video for additional details.
September - February 2019: Ross Fire Flow Improvement - Canyon Road, Pomeroy Road, Newell Road and Monte Alegre Road
MMWD is replacing 115 year-old pipelines in the Town of Ross. Learn more.
September - February 2019: Ross Fire Flow Improvement - Southwood Avenue
MMWD is replacing pipe installed as early as 1903 to improve fire flow to Southwood Avenue. Learn more.
August - December 2018: Slide Repairs at Various Mt. Tam Sites
MMWD is working to repair numerous landslide on the watershed. For schedules, maps and additional details, click here.
September - November 2018: Rice Drive Pipeline Replacement Project in San Rafael
MMWD is installing new pipelines at Rice Drive near the intersection of West Francisco Blvd in the City of San Rafael. Learn more.
June - October 2018: San Rafael Pipeline Replacement Project in Sun Valley
April - September 2018: San Anselmo Pipeline Replacement Project on Butterfield Road
MMWD will install new pipelines in various streets including Butterfield Road, Willow Way, Fairview Court, Rosemont Avenue, Arroyo Avenue, and Sir Francis Drake Boulevard in the Town of San Anselmo. For detour maps and additional information, click here. Traffic control and detours will be in place. Learn more. Update 9/28/18: On Monday, October 8, the contractor will finish paving for this project. This date was chosen because schools are not in session and work hours can be extended. Detours will be in place, and residents can expect delays.
May - October 2018: Sausalito Fire Flow Improvement Project
MMWD will install new pipelines in various streets including Filbert Avenue, Spencer Avenue and San Carlos Avenue in the City of Sausalito. Learn more.
September 2017 - October 2018: Tiburon Fire Flow Improvement Project
MMWD will install new pipeline on Trestle Glen Boulevard and Paradise Drive in the Town of Tiburon. The new water pipeline will replace leak-prone pipe installed as early as 1939 and supplies water to the Town of Tiburon and unincorporated Tiburon from the Alto water tanks, Spring Lane tank, and Ross Reservoir. This project will substantially improve fire flow capacity in the piping for this area. Learn more.