Project Description
Phase II of the Kastania Pump Station Rehabilitation project includes a new roof, drainage upgrades, a new 30-inch check valve, a new electrical motor control center, variable frequency drives, a new surge protection valve and new perimeter fencing.
Benefits
This project updates a critical booster pump station’s electrical equipment to the modern era and allows for improvements to drought resiliency. In conjunction with Phase I, Phase II provides reliability to a 4,300 acre-feet increase in Marin Water’s annual supply.
Schedule and Status
Project currently in design. Construction on hold pending identification of funding.
Expenditure Schedule
Actuals ThroughFY 22 (Rounded) |
FY 23Estimate |
FY 24Estimate |
FY 25Estimate |
Total |
$11,000 |
$110,000 |
$240,000 |
$1,000,000 |
$1,361,000 |
Funding Sources
Capital Maintenance Fund |
Other Funding Sources* |
Total |
$361,000 |
$1,000,000 |
$1,361,000 |