
The Granada Drive Pipeline Replacement Project will install about 10,230 feet of welded steel pipe beneath Granada Drive, a neighborhood street in the Town of Corte Madera. This project replaces aging, leak-prone and seismically deficient piping - some of which was installed as early as 1956.
The project was further accelerated due to failing cast iron pipe, and to work in coordination with the Town of Corte Madera, which will conduct a road resurfacing project in the same area. New water mains will be installed on Estrada Lane, Paloma Drive, Granada Drive, El Camino Drive, Sonora Way and Vista Court. For more information, read Marin Water’s April 2023 Neighborhood Notification Letter for this project.
Project Update (June 10, 2024) Marin Water's contractor began work on this project on Monday, June 10, starting with El Camino Drive. Crews will install and connect new water mains one block at a time to limit neighborhood traffic disruptions. Work is expected to be completed by the spring of 2025. |
Contact Information
Marin Water Construction Management team: 415-945-1560
Maintaining Infrastructure is Top Priority
The pipeline replacement project upgrades aging infrastructure as part of the District's Capital Improvement Program. This project will install seismically resilient pipe and will increase the integrity of the water distribution system.
Project | Granada Drive Pipeline Replacement Project |
Program | A1A02A Replacements - Distribution Pipelines |
Project Number | D23020 |
Contact | Ava Pridgeon | APridgeon@marinwater.org |
Project Description
Installation of approximately 10,230 ft. of 12-inch, 10-inch, 8-inch, 6-inch and 4-inch welded steel piping in various streets in the Town of Corte Madera to replace old leak prone pipe installed as early as 1956 in support of the District's commitment improve the integrity of the water system for reliable conveyance of water to local residents. This project is in coordination with the Town of Corte Madera’s resurfacing project.
Benefits
This project will install seismically resilient pipe and will increase the integrity of the water distribution system.
Schedule and Status
Design: Fall 2023 - Spring 2024
Construction: Summer 2024 - Summer 2025
Funding Sources
Capital Maintenance Fund | Fire Flow Improvement Program Fund | Total |
$5,565,000 | - | $5,565,000 |