Project | Sleepy Hollow Pipeline Replacement Project - Fire Flow Improvement Program |
Program | Pipelines | A2A Fire Flow Improvement Program |
Project Number | F24002 |
Contact | Bryan Cook | bryan.cook@marinwater.org |

Project Description
This project involves the installation of approximately 3,400 feet of 6-inch welded steel pipe to replace undersized, fire flow-deficient and leak-prone 4-inch cast iron pipe.
Benefits
This project will improve fire flow and seismic reliability of the system in support of the District's Fire Flow Improvement Program, a voter-approved initiative that helps boost water flows to hydrants for emergency response purposes.
Schedule and Status
Design: Fall 2024 - Spring 2025
Construction: Fall 2025 - Spring 2026
Funding Sources
Capital Maintenance Fund | Fire Flow Improvement Program Fund | Total |
- | $1,700,000 | $1,700,000 |