This project includes the installation of approximately 6,470 feet of 18-inch, 16-inch, 12-inch, 8-inch, 6-inch and 4-inch welded steel pipe in the City of San Rafael. Work will take place adjacent to Point San Pedro Road, on Lochinvar Road and Knight Drive. The existing pipeline in this area was installed in 1954. This aging infrastructure will be upgraded with seismically resilient, welded-steel pipe, improving water quality now and in the future.
Schedule and Status
Design: Fall 2022 – Spring 2025
Construction: Summer 2025 – January 2026
Project Update:
This project has been completed.
Contact Information
- Marin Water Construction Management team: 415-945-1560
Investing in your water system
The Glenwood Pipeline Replacement Project replaces aging infrastructure as part of the District’s Capital Improvement Program, and is also part of the Fire Flow Improvement Program. Developed together with city and county officials, area fire chiefs and residents, and approved by voters, the Marin Fire Flow Program is being implemented by Marin Water over the next 15 years to address a key public safety concern in the region.
Funding Sources
| Capital Maintenance Fund | Fire Flow Improvement Program Fund | Total |
| – | $3,890,000 | $3,890,000 |