Hind Tanks Replacement (Redwood Tanks)

The Hind Tanks Replacement Project will replace two of the four remaining redwood tanks in the system with steel tanks, improving seismic resiliency to the system.

Schedule and Status

Planning: Summer 2007 – Summer 2023

Design: Summer 2023 – Spring 2027

Construction: Spring 2027 – Fall 2028

Contact Information

  • Marin Water Engineering Team, Zachary Talbott, 415-945-1508

Investing in your water system

This tank replacement project removes two seismically deficient, leak-prone redwood tanks from the Marin Water distribution system, replacing them with steel tanks that are seismically resilient and fire hardened, resulting in in a more resilient water infrastructure system. 

Funding Sources 

Capital Maintenance Fund Other Funding Sources Total
$5,000,000– $5,000,000