The Hind Tanks Replacement Project will replace two of the four remaining redwood tanks in the system with steel tanks, improving seismic resiliency to the system.
Schedule and Status
Planning: Summer 2007 – Summer 2023
Design: Summer 2023 – Spring 2027
Construction: Spring 2027 – Fall 2028
Contact Information
- Marin Water Engineering Team, Zachary Talbott, 415-945-1508
Investing in your water system
This tank replacement project removes two seismically deficient, leak-prone redwood tanks from the Marin Water distribution system, replacing them with steel tanks that are seismically resilient and fire hardened, resulting in in a more resilient water infrastructure system.
Funding Sources
| Capital Maintenance Fund | Other Funding Sources | Total |
| $5,000,000 | – | $5,000,000 |