North Marin Line Stabilization Project

Marin Water will replace two seismically vulnerable San Geronimo Creek pipeline crossings of the North Marin Line (NML) with seismically resistant crossings. The NML was constructed in 1957 to convey raw water from Marin Water’s Kent Lake and Nicasio Reservoir to the San Geronimo Treatment Plant. The existing San Geronimo Creek pipeline crossings are supported on concrete trestles installed in the creek bottom and emerge from the ground through the San Geronimo Creek banks.

As part of this project, Marin Water will replace one pipeline crossing with approximately 1,700 feet of new pipeline within Sir Francis Drake Boulevard. The other pipeline crossing will be replaced with a 36-inch pipeline installed within a single span steel truss supported on drilled piers. Work on the NML will take place seasonally to minimize impacts to the sensitive environmental area surrounding the project site. The Project also includes cutting and removing the existing pipeline and existing piles in San Geronimo Creek.

Project Update (October 2026)
The District selected a contractor for this project in September. The contractor will perform initial work, including potholing, this year, but major field work will begin in the summer of 2027.

Environmental Review Process

Pursuant to the California Environmental Quality Act (CEQA), Marin Water has prepared a Final Supplemental Initial Study/Mitigated Negative Declaration (IS/MND) for the proposed North Marin Line Stabilization Project. The document evaluates potential environmental effects associated with design refinements since adoption of the original 2016 North Marin Line Stabilization Project IS/MND.

The public comment period opened on Oct. 17 and closed on Nov. 26, 2025. Responses to comments received can be reviewed in Appendix D (pages D-1 – D-19). The Final Supplemental IS/MND and Mitigation Monitoring and Reporting Program for the North Marin Line Stabilization Project, and the project itself, was approved by the Marin Water Board of Directors on Dec. 16, 2025, Regular Board of Directors Meeting at 5:30 p.m.

For questions regarding the environmental review, please contact Carly Blanchard, Environmental Planner, at carly.blanchard@marinwater.org. 

Schedule and Status

Construction of initial phases of the NML project is expected to begin in September 2026, and last through October 2027. 

Contact Information

Marin Water Construction Management team:  415-945-1560

Funding Sources 

Capital Maintenance Fund Fire Flow Improvement ProgramTotal
$1,094,000–$1,094,000