This project replaces the existing 20,000-gallon redwood water storage tank with a bolted steel tank of the same size. The existing tank is one of just four remaining redwood tanks, is leak-prone and is more than 40 years old.
Project update (August 2026)
A preconstruction meeting was held on June 30. The contractor is working to procure necessary project materials. The project is anticipated to be ongoing through spring 2027 dude to 6-month lead time in fabricating the tank.
Schedule and Status
Design: Spring 2025-Winter 2026
Construction: Spring/Summer 2026-Fall 2026
Contact Information
- Marin Water Construction Management team: 415-945-1560
Investing in your water system
Through the District’s long-standing Redwood Tank Replacement Program, we continue to prioritize these tanks for replacement, helping to build a more reliable, resilient water system.
Funding Sources
| Capital Maintenance Fund | Other Funding Sources | Total |
| $715,024 | – | $715,024 |